inewsmagazine

New Ideas

Long Mott Energy gets NRC permit to build four X-energy small reactors in Texas

Issued November 9, the permit covers an 800-megawatt-thermal gas-cooled plant; the NRC calls it the first such construction permit in nearly 60 years.

By Ideas Desk ·

The short version

  1. The NRC issued construction permit CPAR-3 on November 9, 2026, to Long Mott Energy, LLC, which a 2025 NRC notice describes as a wholly owned subsidiary of the Dow Chemical Company.
  2. The Long Mott Generating Station in Calhoun County, Texas, is designed as four X-energy Xe-100 small modular reactors with 800 megawatts of thermal output.
  3. The NRC found the company technically and financially qualified to build the plant. The permit took effect immediately.
  4. A licensing board admitted San Antonio Bay Estuarine Waterkeeper as a party to contest the application in January 2026; an NRC notice later listed an appeal of board decisions ending that proceeding.

The Nuclear Regulatory Commission issued a construction permit on November 9, 2026, to Long Mott Energy, LLC, for a nuclear plant in Calhoun County, Texas, according to a notice of issuance in the Federal Register on November 12. An NRC notice from June 2025 describes Long Mott Energy as a wholly owned subsidiary of the Dow Chemical Company; the permit notice names only Long Mott Energy. The Long Mott Generating Station is designed as an 800-megawatt-thermal plant made up of four Xe-100 small modular high-temperature gas-cooled reactors, a design from X-Energy, LLC, according to a hearing notice published in August.

On the NRC's list of 2026 news releases, the agency titles its November 9 announcement "NRC Issues First Construction Permit in Nearly 60 Years for High-Temperature Gas-Cooled Reactor". We could not open the release itself, so the details here come from the agency's Federal Register notices.

What the permit allows

The permit, numbered CPAR-3, took effect immediately and authorizes Long Mott Energy to build the reactor facility described in its application. In issuing it, the NRC found that the application met the Atomic Energy Act and the agency's rules, that safety questions would be satisfactorily resolved by the time construction is complete, and that the plant could be built and run at the site without undue risk to public health and safety, subject to the permit's conditions. It also found the company technically and financially qualified to build the plant.

The notices cover construction. They describe no approval to operate the plant, and they give no cost, construction schedule or start date for it.

From application to permit

The company applied by letter on March 31, 2025, and NRC staff told it by letter dated May 12, 2025, that the application had been accepted for review. By our count, the permit came about 19 months after the application. Along the way, the company filed a revised application in September 2026, the agency set the mandatory, uncontested hearing on the application, called under section 189a of the Atomic Energy Act, for September 22, 2026, in Port Lavaca, Texas, and NRC staff completed a safety evaluation dated October 30, 2026.

Long Mott Generating Station: steps in the NRC review, from NRC notices in the Federal Register
DateStep
March 31, 2025Construction permit application filed
May 12, 2025NRC staff letter accepting the application for review (docket 50-614)
January 22, 2026Licensing board admits San Antonio Bay Estuarine Waterkeeper as a party
September 18, 2026Revised application (Revision 1)
September 22, 2026Mandatory hearing scheduled in Port Lavaca, Texas
October 30, 2026NRC staff safety evaluation
November 6, 2026Commission affirmation session scheduled (tentative) on an appeal of board decisions ending the contested proceeding
November 9, 2026Construction permit CPAR-3 issued

A contested hearing on the docket

The application also drew a challenge. San Antonio Bay Estuarine Waterkeeper filed a petition to intervene after the NRC's June 2025 notice; the agency received it on August 11, 2025. On January 22, 2026, the NRC's Atomic Safety and Licensing Board found that the group had standing and had submitted a contention that was partly admissible, and admitted it as a party, according to the board's February 2026 notice. That notice said a hearing would be held and that the board might hold evidentiary hearings. The NRC's August 2026 hearing notice still described the proceeding as ongoing. A Commission meeting notice published on November 10 then listed, for November 6, a tentative affirmation session on an "Appeal of Board Decisions Resulting in Termination of Proceeding" in the case. The permit notice does not mention the proceeding, and the documents we read do not say when or why the board's decisions ended it, who appealed, whether or how the Commission ruled or what the group's contention argued.

An advanced reactor design

The plant is handled by the NRC's advanced reactor staff: the notice of issuance is signed by a director in the agency's Office of Advanced Reactors, and the 2025 notice describes the four-unit facility as a high-temperature gas-cooled reactor and classes it as a non-light-water reactor. The release title quoted above presents the permit as the first for a high-temperature gas-cooled reactor in nearly 60 years. Three days later, the NRC's release list shows another announcement, titled "NRC Streamlines Advisory Committee Role To Support Advanced Nuclear Licensing", which we did not open.

Sources

  1. Long Mott Energy, LLC; Long Mott Generating Station; Construction Permit (notice of issuance, FR Doc. 2026-23029) Nuclear Regulatory Commission, via the Federal Register (GovInfo), November 12, 2026
  2. Long Mott Energy, LLC; Long Mott Generating Station; Notice of Hearing (FR Doc. 2026-16975) Nuclear Regulatory Commission, via the Federal Register (GovInfo), August 20, 2026
  3. Long Mott Energy, LLC; Long Mott Generating Station; Construction Permit Application (FR Doc. 2025-10505) Nuclear Regulatory Commission, via the Federal Register (GovInfo), June 10, 2025
  4. Atomic Safety and Licensing Board Panel, Long Mott Energy, LLC, Memorandum and Order (Notice of Hearing) (FR Doc. 2026-03415) Nuclear Regulatory Commission, via the Federal Register (GovInfo), February 20, 2026
  5. Sunshine Act Meetings, week of November 2, 2026 (FR Doc. 2026-22869) Nuclear Regulatory Commission, via the Federal Register (GovInfo), November 10, 2026
  6. News releases, 2026 Nuclear Regulatory Commission, November 15, 2026

Researched and drafted with AI assistance, then checked against the 6 sources above in a separate fact-check on November 15, 2026. Spotted an error? Tell us.

Read next

  1. New Ideas · Explainer

    What a public benefit corporation is, and what Anthropic's IPO filing says the form will mean

    Anthropic, which expects to price its IPO on November 18, is a Delaware PBC, so its board must balance investors' interests with a stated public benefit.

    · 4 min read

  2. New Ideas

    Andromeda Robotics reports $30 million in stock sales and says its companion robot is now in US senior care

    A Form D lists $30.0 million sold of $75 million. The company says Abi is in a California memory care home whose operator works with UC Davis researchers.

    · 3 min read

  3. New Ideas

    South Korea's financing backed by patents and other IP reached 12.4 trillion won in 2025, WIPO report says

    Investment overtook guarantees last year in a market that grew from 4.84 trillion won in 2020, the report says; the goal now is one led by private finance.

    · 3 min read